Class P means the site has a problem or condition that ordinary normal-site reactivity classification alone does not adequately describe. It does not show that a house has failed or that it needs piles or underpinning. Ask why the practitioner classified this particular site P.

For a building project requiring structural design, explore our structural and foundation design. An article cannot determine the cause or appropriate solution for an individual property.

Illustration of site conditions relevant to a Class P classification.
Illustration of site conditions relevant to a Class P classification.
Illustration of site conditions relevant to a Class P classification.

P has more than one possible reason

Class P can reflect inadequate bearing strength, potentially excessive settlement, certain fill conditions, landslip, mine subsidence, collapsing or erodible soils, abnormal moisture or other influences outside normal reactive-soil assumptions.

Deep fill, tree-related drying and possible slope instability need different information. Two sites marked P may therefore lead to quite different footing designs.

The reason belongs in the report

The classification report should identify why the site is Class P and recommend further geotechnical investigation where more information is needed for design.

If a quotation or drawing says only Class P, ask for the underlying report. Find out whether the reason has been investigated, which assumptions the designer adopted and whether any recommended work is still outstanding. The commentary to C2.1.2 says that P alone will not usually give enough information to prepare an appropriate footing design.

A classification investigation is not always a complete design investigation

A completed soil test does not confirm that every ground question relevant to a Class P footing design has been resolved. Ask what investigation is still needed.

Ask what extra investigation would establish and whether the findings could change the design. Repeat testing may still be needed and there is no guarantee of a lower price, but the team should be able to explain what each test is for.

P does not select the remedy for an existing crack

Standard deemed-to-comply designs do not cover Class P sites. A site-specific engineering response must address the actual condition, not substitute a generic heavier slab or deeper pile. A letter on a soil report is also not a retrospective explanation of damage in an existing building.

Keep the classification report, design response, proposed site works and unresolved assumptions together. Record any existing distress or movement separately. Seek prompt assessment for urgent change or apparent instability, regardless of the site class.